An extension of the scope of HUNÉP’s contract to build SENSIRION’s new plant
- 2020-08-08

HUNÉP signed the amendment of the contract for additional elements of the technical implementation.
On 7 August 2020, the contract concluded on 23 June for the construction of Sensirion’s manufacturing plant was amended with the following technical content added to its scope:
- the full-scale construction of the building facades;
- the full-scale construction of the roof structure;
- lower and upper floor layer courses up to the concrete bottom plate below the floor covering, also including the floors of the logistics and manufacturing areas on the lower floor;
- building engineering basic wiring and piping.
The deadline for the completion of the works is early next year.