An extension of the scope of HUNÉP’s contract to build SENSIRION’s new plant

  • 2020-08-08

HUNÉP signed the amendment of the contract for additional elements of the technical implementation.

On 7 August 2020, the contract concluded on 23 June for the construction of Sensirion’s manufacturing plant was amended with the following technical content added to its scope:

  • the full-scale construction of the building facades;
  • the full-scale construction of the roof structure;
  • lower and upper floor layer courses up to the concrete bottom plate below the floor covering, also including the floors of the logistics and manufacturing areas on the lower floor;
  • building engineering basic wiring and piping.

The deadline for the completion of the works is early next year.